Machine name: NLUTSRSP03
 

Standard scope of Mergor: 

Phase 0: Design report

  • Producing design report
  • Planning OTAO® activities
  • Producing engineering plans

    Phase 1: Design and engineering
  • Determining loads involved in transport and immersion
  • Processing salt/fresh water quality data
  • Design of temporary bearings (tiles and pins)
  • Dimensioning and detailed specification of transport and immersion
  • Prestress Dimensioning of ballast tanks
  • Dimensioning of OTAO® suspension points
  • Determining deck layout
  • Determining transport and  immersion loads
  • Dimensioning mooring system
  • Dimensioning dock winch system
  • Dimensioning immersion site winch system
  • Design of closure joint frame
  • Recommendation on choice of 'Gina' gasket profile
  • Dimensioning closure joint wedges
  • Dimensioning bulkheads
  • Dimensioning underflow system
  • Processing of as-built dimensional data
  • Dimensioning of the Jacking System for horizontal positioning
  • Outline dimensional characteristics during immersion

Phase 2: Preparation

  • Drafting scenarios and activity plans
  • OTAO® coordination during casting of tunnel elements
  • Producing dimensional plan for sinking
  • Positioning and dimensioning foundation tiles
  • Dimensioning tunnel elements for sinking
  • Dimensioning immersion trench (third parties)
  • Dredging immersion trench (third parties)

Phase 3A: Construction of casting basin and temporary mooring location

  • Floating and shifting TE
  • Winching out TE
  • Transporting TE to temporary mooring site
  • Preparing temporary mooring site (excl. buoys, lighting etc.)
  • Making TE ready for immersion
  • Installing shaft and survey tower
  • Filling ballast tanks and checking for leaks
  • Emptying TE ballast tanks
  • Installing winches on anchors and working platforms developed by us and made available by you
  • Preparing immersion pontoons
  • Securing immersion pontoons to TE
  • Attaching fenders to TE
  • Checking navigation depth of access channel for keel clearance
  • Attaching winch lines to TE by divers

Phase 3B: Work at the immersion site

  • Setting out anchors and installing winch pontoons
  • Installing anchor points on shore for forward lines
  • Transporting TE to immersion site
  • Making immersion trench ready (survey/ /anchor points etc.)
  • Installing anchors
  • Installing winches
  • Attaching winch lines to TE by divers
  • Securing TE in winch lines
  • Seeking sheltered site in fast current conditions
  • Attaching forward lines
  • Miscellaneous diving work
  • Loading TE with ballast to immersion weight
  • Immersing TE
  • Dimensioning during immersion
  • Diver check of 'Gina' gasket
  • Positioning of jacks on foundation tiles, check by divers
  • Attaching horizontal pulling cylinders (by divers)
  • Fastening TE
  • Emptying immersion joint
  • Check of TE position
  • Jack corrections of TE position
  • Check of immersion trench
  • Under flowing TE
  • Check measurements of under flowing reaction forces
  • Removing towers and jacks 
  • Backfilling and covering immersion trench 
  • Diving work for the immersion operation

Possible supplies (temporary nature)

  • Deck layout
  • Bulkheads 
  • Ballast water system
  • Pontoons
  • Winches and fastenings
  • Ducts
  • Bulkhead doors
  • Access shafts
  • Measurement masts
  • Tugs
  • Sheer legs and pontoons
  • Under flowing sand
  • Sand injection installation
  • Support vessels
  • Jacks

Outside standard Mergor scope;

  • Permits
  • Accommodation on site
  • Communication facilities including telephone, fax and internet connections
  • Consequences of wind on the immersion operation
  • CAR insurance
  • etc. (more details to follow)